2014 2015 2016 a During 2014 Nilsen Company started a constr
2014
2015
2016
(a)
|
Solution
Percentage cpmpletion stage 2014 2015 2016 Cost to date 395200 846880 1078000 Estimated cost to complete 592800 225120 0 Total cost 988000 1072000 1078000 Estimated completion stage 40% 79% 100% (Cost to date/ Total cost)*100 Gross profit to be recognized 2014 2015 2016 Contract price 1736000 1736000 1736000 Less: Estimated Total cost 988000 1072000 1078000 Gross Profit for the contract 748000 664000 658000 % percentage completion 40% 79% 100% Grofit to be recognized 299200 524560 658000 Less: Gross profit recognized in earlierr years 0 299200 524560 Gross profit recognized in current year 299200 225360 133440 Year Gross recognized 2014 299200 2015 225360 2016 133440